Oroville Fix Update

The headline today, Governor Brown waived some environmental reviews on emergency construction at Oroville Dam. But look at the last paragraph in the story.

Authorities say designs for the redone main spillway are about 60 percent complete. State water officials still aren’t releasing an estimated price tag for the rush repairs, but say they hope to award contracts for the work by April 17.

Fact 1
OK, it’s close of business on April 6th. The state Department of Water Resources says the plans for the fix (temporary one per previous media reports) are 60 percent completed.

Fact 2
They hope to awards contracts by April 17th.

They are finishing the plans, soliciting bids, and deciding who will be awarded the contract seven business days from now? What could possibly go wrong with that plan?

Conclusion
Either the fix is in on who will be awarded this contract or these guys are dumber than dirt to think they can get a bid price with unfinished plans. Oh, change order is spelled $$$$$$